پل و سازه‌های فلزی

MSA Engineering & Construction Co. has extensive experience and capabilities in the fabrication, erection and execution of heavy steel structures, bridges and major infrastructure projects.

The company's capabilities in this field cover a wide range of structures, including arch bridges, truss bridges, cable-stayed bridges, composite and plate-girder bridges, urban flyovers and heavy industrial steel structures with significant dimensions and weights.

Its experience in major projects, together with its fabrication and erection resources, enables the company to participate in complex bridge and heavy steel structure projects.

Areas of Expertise

  • Fabrication and erection of steel bridges

  • Construction and erection of arch and truss bridges

  • Fabrication and installation of composite and plate-girder bridges

  • Construction and erection of cable-stayed bridges

  • Fabrication and erection of heavy steel structures

  • Execution of large-scale industrial and infrastructure steel structures

  • Erection of steel structures under demanding site conditions

Selected Bridge Projects

Karun 3 Arch Bridges

MSAEC participated in the fabrication and erection of two major arch bridges associated with the Karun 3 project.

First Bridge:

  • Type: Open-spandrel arch bridge

  • Arch height: 42 m

  • Arch cross-section: 8 × 9 m

  • Arch span: 264 m

  • Total deck length: 283 m

  • Deck width: 11.8 m

  • Weight: approximately 2,500 tons

Second Bridge:

  • Type: Open-spandrel arch bridge

  • Arch height: 40 m

  • Arch cross-section: 8 × 9 m

  • Arch span: 177 m

  • Total deck length: 216 m

  • Deck width: 11.8 m

  • Weight: approximately 1,700 tons

Shahid Jahan Ara Bridge – Khorramshahr

The Shahid Jahan Ara Bridge is one of the company's notable composite bridge projects.

  • Type: Tied arch and composite girder

  • Total length: 384 m

  • Arch length: 144 m

  • Arch radius: 120 m

  • Width: 15 m

  • Weight: approximately 1,535 tons

Sosangerd Bridge

A tied-arch bridge project with the following specifications:

  • Type: Tied arch

  • Length: 52 m

  • Width: 12 m

  • Weight: approximately 170 tons

Karun 3 Truss Bridge

A truss bridge associated with the Karun 3 project:

  • Number of spans: 3

  • Total length: 99 m

  • Width: 5 m

  • Weight: approximately 160 tons

Sheikh Shooshtari Bridge

A tied-arch bridge constructed over the Karun River:

  • Arch span: 84 m

  • Total length: 118 m

  • Width: 12.3 m

  • Weight: approximately 450 tons

Bafgh–Bandar Abbas Railway Bridges

Space-truss railway bridges with the following specifications:

  • Type: Space truss with trapezoidal cross-section

  • Total length: 800 m

  • Width: 9 m

  • Height: 45 m

  • Weight: approximately 4,000 tons

Composite and Urban Bridges

MSAEC has also participated in the fabrication and erection of composite and plate-girder bridges, including:

Quaid-e-Azam (Clifton) Flyover Bridge – Karachi, Pakistan

A composite plate-girder bridge with a length of 606 m, width of 15.4 m, maximum height of 17.25 m and weight of approximately 2,300 tons.

Abadan Piroozi Bridge

A continuous composite-girder bridge with a length of 340 m, width of 15 m, maximum height of 8 m at the river center and weight of approximately 1,311 tons.

Karheh Bridge

A composite plate-girder bridge with a length of 203.5 m, width of 12 m and weight of approximately 850 tons.

Shisha Bridge – Bangladesh

A composite bridge with a length of 202 m, width of 5.1 m, span of 40.5 × 5 m and weight of approximately 210 tons.

Abadan Bahmanshir Bridge

A continuous composite-girder bridge with a length of 310 m, width of 13 m and weight of approximately 1,000 tons.

Navab Flyover – Tehran

A composite plate-girder flyover with a total length of 780 m plus 300 m of approach roads, width of 42 m and weight of approximately 3,300 tons.

Ashrafi Esfahani Flyover – Tehran

A composite-girder flyover with a length of 310 m, width of 13 m and weight of approximately 1,000 tons.

Niyayesh Flyover – Tehran

A composite box-girder flyover with a length of 360 m, width of 11.5 m and weight of approximately 1,000 tons.

Shahid Hemmat Flyover – Tehran

A composite box-girder flyover with a length of 130 m, width of 22 m and weight of approximately 800 tons.

Major Cable-Stayed and Arch Bridges

Karun 4 Cable-Stayed Bridge

The Karun 4 Cable-Stayed Bridge was constructed over the Karun 4 reservoir in Chaharmahal and Bakhtiari Province.

The bridge has a main span of approximately 210 m and a total length of approximately 379.5 m, providing a road connection across the reservoir area.

Karun 4 Large Arch Bridge

The Karun 4 Arch Bridge has a main span of approximately 300 m and a total length of 378 m. The bridge deck is approximately 11.8 m wide and accommodates two-way traffic and pedestrian walkways.

The total structural weight is approximately 3,875 tons.

Heavy Steel Structures

Boeing 747 Hangar – Mehrabad Airport

One of the company's notable heavy steel structure projects is the fabrication and erection of an aircraft hangar at Mehrabad Airport in Tehran.

The hangar has a capacity for four Boeing 747 aircraft. A major part of the project involved the fabrication and erection of four steel structures with a combined weight of approximately 710 tons, a span of 156 m and an elevation of 36 m.

Yazd Alloy Steel Company

The erection of the steel structure of Yazd Alloy Steel Company, with an approximate weight of 7,300 tons, consisted of six sections with spans ranging from approximately 22 to 36 m. The scope also included related machinery and industrial foundations.

Other Heavy Steel Structure Projects

The company's experience also includes the erection of steel structures for various industrial projects, including:

  • Al-Mahdi Aluminium Complex in Bandar Abbas – approximately 3,267 tons

  • Shahid Rajaei Thermal Power Plant structures, including turbine halls and control buildings – approximately 10,100 tons

  • Dorus Tower, 18 floors – approximately 2,100 tons

  • Tehran Municipality parking structure – approximately 600 tons

  • Heavy Metallurgy Workshop at MSA Factory – approximately 3,500 tons

  • Development structure of Arak Aluminium Company – approximately 1,500 tons

  • Repair and replacement of the steel structure of the Dolphin floating dock – approximately 8,000 tons

  • Steel structure erection for the ship repair unit of Farasahil Industries – approximately 10,000 tons

Drawing on its experience in major bridge and heavy steel structure projects, MSA Engineering & Construction Co. is capable of participating in infrastructure and industrial projects, from fabrication and preparation through erection and execution of complex structures.

Expertise, Experience and Commitment – Our Foundation for Building Major and Lasting Structures.